Chinese | English
Installation and commissioning of two-step expanding machine
Installation and commissioning of two-step pipe expanding machine
Two step pipe expanding machine according to the manufacturer to provide the foundation of interchanged figure for installation, equipment installation should use level measurement to find good level, the level of degree of mean error of plus or minus 20 mm after looking for a good level and center line, fix the whole equipment.
Two step pipe expanding machine before they go out, pump stations, hydraulic pipe expanding machine, intermediate frequency power supply has been debugged and equipment to the buyer, after sent by the equipment manufacturer guidance according to install and debug.